The skyline on the Fylde Coast is changing on a daily basis as Mill Farm races towards the summer opening date.
All the terracing, bar the steps, on the West Stand is complete and the mechanical and electrical instillation in the stadium is well underway.
The roof canopy has been rolled out and will be finished over the next week, whilst the blockwork on the ground floor is starting to take shape.
The rain water harvesting tent has been put down ahead of the start of the pitch work and the impressive wall at the entrance of the development has been constructed.
Our neighbours Aldi are also well on their way constructing their new store as you can see from our gallery below.