Our exclusive Mediterranean restaurant Milano’s is fast approaching completion with less than a week until the soft opening.
The original open date was delayed as we made some alterations and after walking around the place it has certainly been worth the extra effort put in by our fantastic team.
The three circular seating booths are built and fixed in place and now just await the white leather upholstery, due to arrive early next week.
Over 80% of the parquet flooring that runs throughout the restaurant is fitted whilst the final touches to the decorations will be applied next week.
The glazed screens dividing up some of the seating booths have been fitted, whilst both the beautiful ladies and gents toilets have been finished, complete with fabulous new mirrors this week.
And perhaps most importantly the kitchen has been commissioned and is ready to serve up some delightful dishes!
Elsewhere on site we have opened additional parking at the stadium (150 spaces) to ease parking issues on matchdays.
Euro Garages are well on with construction of their petrol station with the steel framework visible on the entrance into the development.
Finally work continues on our 3G football and hockey pitches and we even went to the trouble of sending a drone up to give you an ideal of the impressive scale of the project!