It has been all systems go at Mill Farm this week.
Another good week of weather has helped contractors really forge ahead and staff were brought in at the weekend to make the most of the conditions.
The steel works on the West Stand are now 80 per cent complete and the structure is now sitting proud on the skyline.
Aldi contractors have also arrived on site as they start preparation work for their new store.
The kerbs and tarmac base course has been completed for the main stadium car park and the overflow car park and water and gas lines have been laid and are being backfilled.