THIS week things are really moving and if you haven’t been to have a look yet get yourself down, it’s pretty impressive!
The first deliveries of steel for the main stand have arrived and are being installed and a total of 340 tonnes of steel will be delivered and erected over the coming weeks. (See the pictures below.)
The West stand is the flagship of the complex and it will take seven weeks to erect the steel framework, which at its highest point will be 18m.
Foundation work has also begun on the East Stand ahead of that steel work being erected.
Elsewhere on site, all the main drainage is now completed and the final section of the spine road is being built up ready for tarmacing in a fortnight.